« Back to News & Notices

GREAT NEWS - ENTERGY IS SET TO BEGIN WORK

We have great news.  Entergy is scheduled to begin work installing the new three-phase eletrical lines at the new water treatment plant on March 15th.  They anticipate it taking two weeks to complete the installation.  Once this is done Watson Wells will test the pumps and Peck Construction will install all communication modules along with finalizing all the loose ends needed before we can begin filtering water to the system.

Hopefully we will be fully operational by the middle of April.