Look here to find information on current projects happening in our community to enhance your water service.
"Subscribe" and receive updates on our Current Projects the minute they are posted. It's easy!
Water Treatment Plant after Hurricane Laura
September 01, 2020
We did receive a small amount of damage from Hurricane Laura. Peck Construction was onsite the next day making repairs. We do not think this will delay the project.
Riverton Water Treatment Plant
August 25, 2020
The treatment plant is moving along. The ground storage tank is up and the treatment building is going up. We anticipate the treatment plant being up and inline working by early 2021.
Water System Improvement Contract #2 - New Water Treatment Plant
January 06, 2020
If you see red flags around your meter please do not remove. These flags are being used to mark the existing meters that are being replaced with radio read meters.
Construction to begin on new water treatment plant located in Riverton, LA.
Replace 4" line with 6" line on Hwy 4 East
Install radio read meters
Water System Improvement Contract #1 - Riverton Wells (2)
January 06, 2020
Due to COVID19 the drilling contractor has suspended work.
New construction begins on two new wells located in Riverton, LA.
Davis Lake Nursery Project (COMPLETED)
May 08, 2019
Louisiana Department of Health issued our permit on May 06, 2019 to begin working on the Davis Lake Nursery Project. This is an extension of approximately 2,800 feet of a new 6" water main along Nursery Road, several water meters and two fire hydrants.
Work is currently scheduled to begin the last week of May.